Technical design, delivery, montage works and putting in operation of the WWTP 2 Selcha
Client:
Municipality of Devin
Scope of Work:
Technical design, supply and installation of technological equipment and WWTP 2 Selcha commissioning
Capacity:
600 PE
Overview:
The technological design includes:
Preliminary treatment – primary sedimentation tank which also works as a sludge storage tank; storage tank for pretreated wastewater; pumping station;
Biological treatment – two stages of submerged aerated biofilters with fixed biomass and sedimentation in secondary clarifier, using activated sludge processes to provide low – cost and stable purification of the wastewater;
Disinfection with NaOCl in cases of epidemic;
Sludge transportation to a regional waste disposal site or for agricultural use.